Victorian Sliders: glass plant channel drainage
Meticulously planned to eliminate factory downtime, Starkey Developments installed 70 metres of D400 channel drainage within the Victorian Sliders glass plant over a bank holiday weekend.
From Thursday afternoon floor cutting to Monday afternoon handover, the programme was coordinated around the factory shutdown, ready for manufacturing to resume with the Monday night shift.
Thursday and Friday: preparation
Saw-cutting began Thursday afternoon. On Friday, excavators broke out the floor and excavated to level, with external works connecting to an existing manhole outside.
Saturday: 70 m of D400 drainage
The team laid 70 metres of D400 channel drainage, carefully setting the channels level with the existing concrete slab.
Sunday: concreting and finishing
Concrete was placed either side of the channel drains and float finished to complete the reinstatement around the new drainage runs.
Monday: cleaning and handover
The site was cleaned before handover on Monday afternoon, ready for the night shift of manufacturing to begin.