A complete transformation of an existing yard area at Wynnstay, creating a dedicated base for a new 55,000-litre steel bunded diesel tank, a 5,000-litre AdBlue tank and storage, with secure fencing and vehicle impact protection.
From breaking out the old concrete through to the finished installation, Starkey Developments delivered the groundworks, reinforced base and associated external works.
Site preparation
Breaking out the existing concrete base using our excavator and hydraulic breaker, removing the old material and preparing the area for the new slab.
Reinforced concrete base
Formwork and steel reinforcement installed before placing and finishing the new concrete base, with a brushed surface and neatly finished edges.
Security fencing and access
Green steel palisade fencing and gates installed around the diesel, AdBlue and storage area, providing a secure enclosure with access to the equipment.
Vehicle protection and lighting
Galvanised Armco barriers with high-visibility yellow ends installed around the base, together with external lighting serving the area.